Nuclear decommissioning project in Cumbria: over 4 years ahead of schedule and set to save £30 million

Posted by: , Posted on: - Categories: Innovation/savings
PCM Programme at Low Level Waste Repository, near Drigg in Cumbria, over 4 years ahead of schedule and set to save £30 million

Carl Smith, PCM Decommissioning Senior Project Manager at Low Level Waste Repository Ltd, describes how hard work, dedication and commitment has led to a demolition project being at least 4 years ahead of schedule and forecast to save £30 million compared to its original cost forecast.

Learning from experience helps shift radioactive waste at Hunterston A site in Scotland

Posted by: , Posted on: - Categories: Innovation/savings, Waste management
Hunterston Bunker 4 and 5 from Bunker 5 entrance

Stuart Blair, Higher Activity Waste Production Manager at Magnox Ltd, describes how lessons learned have meant that the second of Hunterston’s five concrete waste bunkers has now been successfully emptied of its hazardous contents – using 23 less containers than the first bunker clearance, and completing 6 weeks ahead of schedule.

Successful radioactive waste retrieval from underground chambers at Berkeley site in Gloucestershire

Posted by: , Posted on: - Categories: Innovation/savings, Waste management
Inside the Fuel Element Debris (FED) vault at Berkeley nuclear site in Gloucestershire

Paul Oswald, Site Delivery Manager at Magnox Ltd, describes how, 50 years after its accumulation and a number of failed attempts to retrieve it, a uniquely complex range of mixed waste is finally being retrieved from the vaults where it was kept. Find out more about the work to ensure safe storage of this radioactive waste.

“Building blocks” and “stepping stones” for a career in nuclear decommissioning

Posted by: , Posted on: - Categories: Skills, Supply Chain
Civil engineer Jack Hardy spent eight months with the NDA as part of the nucleargraduates training scheme and now works for Nuclear Advanced Manufacturing Research Centre (NAMRC).

Civil engineer Jack Hardy spent 8 months with the NDA as part of the nucleargraduates training scheme and now works for Nuclear Advanced Manufacturing Research Centre (NAMRC). He describes how the varied experience built up his understanding of the industry, developed a network of contacts and led to an ongoing involvement with the NDA’s mission.

A 120-year mission: securing the skills needed for UK nuclear decommissioning

Posted by: and , Posted on: - Categories: Skills, Socio-economic
NDA's mission 2015 to 2120

Natasha Hanson, Head of HR Strategy and Delivery, and Beccy Pleasant, Head of Skills and Talent, describe the challenges around maintaining a skilled workforce for such a long-term mission. They share the work underway to overcome these challenges, and seek your views on this approach.

NDA investment of more than £7m leverages an additional £39m for Meirionnydd and Anglesey

Posted by: , Posted on: - Categories: Socio-economic
Socio-Economic-funding---Meirionnydd-and-Anglesey

Jon Phillips, NDA’s Director of Communications, celebrates investment for north-west Wales and explains why supporting efforts that help mitigate the impacts of decommissioning on local communities is an important part of the NDA’s remit.